Overview
The LAX Delta Relocation Enabling Project allowed Delta Air Lines to move from Terminals 5 and 6 to Terminals 2 and 3, while the twenty-two airlines in Terminals 2 and 3 moved to Terminals 5 and 6 at the same time. It was the largest airline relocation in aviation history. S&P coordinated with multiple stakeholders and the airport authority to upgrade and expand the existing baggage handling system (BHS) while airline operations continued. S&P completed multiple critical path tie-ins and finished all critical path scope on or ahead of schedule, keeping change order costs under 5% of the total BHS contract value.

Details
S&P Services:
- Construction management
- Project controls
- Quality assurance and quality control program
- Testing and commissioning
- Project close-out
- Cost control
Owner
Delta Air Lines
Location
Los Angeles, CA
Size
658,000 SF